Every EVM and Primavera P6 term you'll see in a controls report, explained in plain English with worked examples. Bookmark it — your PMs will use it.
% Complete
KPIPercent Complete
How much of the total planned work has actually been finished, expressed as a percentage.
Read the full definition
Actual Cost (AC)
methodActual Cost / Spent
The real money you've spent so far. Every invoice, every timesheet, every PO.
Read the full definition
AI Direction
productAI-Generated Recommendations
Plain-English guidance from GPT-5.6 Terra on where to focus, why the numbers moved, and what to do next. Not a black box — every insight cites the KPI that triggered it.
Read the full definition
BAC
KPIBudget At Completion
The original approved budget for the whole project. What it should cost from start to finish if everything goes to plan.
Read the full definition
CPI
KPICost Performance Index
Are we getting a dollar of work for every dollar we spend? 1.00 means on-budget, under 1.00 means over-budget (you're paying more than you're earning).
Read the full definition
CV
KPICost Variance
Earned Value minus Actual Cost. In dollars, how far ahead or behind you are on budget. Negative = over-budget.
Read the full definition
Data Date
methodData Date (Cutoff Date)
The 'as of' date for the numbers on screen. Everything to the left is actual history. Everything to the right is forecast.
Read the full definition
Discipline
methodDiscipline (Trade/Craft)
A category of work grouped by skill or system — Civil, Mechanical, Electrical, Piping, Instrumentation, etc. Breaking data out by discipline shows exactly which crew is dragging the project.
Read the full definition
EAC
KPIEstimate At Completion
The current forecast of what the project will actually cost at the finish line — based on how it's really performing.
Read the full definition
Earned Value (EV)
methodEarned Value / Budgeted Cost of Work Performed
The value of work you have actually completed, priced at the original budget rate. This is your true progress — not just hours logged.
Read the full definition
EPC
industryEngineering, Procurement & Construction
A common contract model where one firm handles the full lifecycle: designing (Engineering), buying the equipment (Procurement), and building it (Construction). Typical for large industrial and energy projects.
Read the full definition
ETC
KPIEstimate To Complete
How much more money you still need to spend from today until the project is done.
Read the full definition
EVM
methodEarned Value Management
The industry standard for measuring project health. It compares three things at any point in time: what you Planned, what you Earned, and what you Spent — and uses the gap to predict where you'll land.
Read the full definition
Fiscal 4-4-5 Calendar
product4-4-5 Fiscal Calendar
A common finance calendar where each quarter is split into three months of 4, 4, and 5 weeks. Every period always ends on a Saturday — making weekly reports line up cleanly with month-end.
Read the full definition
Forecast Overrun
KPIProjected Cost Overrun at Completion
How much you'll be over budget when the project finishes if today's performance continues. Calculated as BAC minus EAC.
Read the full definition
Planned Value (PV)
methodPlanned Value / Budgeted Cost of Work Scheduled
The value of work that should have been completed by today, according to the baseline schedule.
Read the full definition
S-Curve
chartCumulative Progress Curve
The chart that shows spend or progress adding up over time. It usually looks like a stretched S — slow start, steep middle, slow finish. Overlaying Planned, Earned, and Spent instantly reveals if you're drifting.
Read the full definition
Snapshot
productProgress Snapshot
One row of weekly (or monthly) progress data: how many hours were planned, earned, and spent by each discipline for that period.
Read the full definition
SPI
KPISchedule Performance Index
Are we finishing work as fast as we planned? 1.00 means on-schedule, under 1.00 means behind schedule.
Read the full definition
SV
KPISchedule Variance
Earned Value minus Planned Value. In dollars, how far ahead or behind you are on schedule. Negative = behind.
Read the full definition