KPI
SPI
Schedule Performance Index
Plain English
Are we finishing work as fast as we planned? 1.00 means on-schedule, under 1.00 means behind schedule.
Worked Example
SPI 0.91 → For every planned week of work, you actually completed 0.91 weeks — about 9% behind.