Sample Project
Utah Power · Salt Lake City, Utah, United States · Data Centers
Data Center Sample
PM: Michael Cain · Disciplines: 12 · Data Date: 2026-08-22
At Risk
Running in Hours-First Mode — Industry-Standard Labor EVM
All KPIs (CPI, SPI, CV, SV, BAC, EAC, ETC, VAC) are computed from hours. Add a Cost column to your next import to unlock dollar-denominated forecasts on top.
Key Performance Indicators
% CompleteYELLOW
70.0%
Spent 74.2%
% Complete = Earned Hours ÷ BAC × 100
CPIYELLOW
0.94
CV -84.4K h
CPI = Earned Hours ÷ Spent Hours
SPIYELLOW
0.91
SV -141.7K h
SPI = Earned Hours ÷ Planned Hours
EACRED
2.12M h
BAC 2.00M h
EAC = BAC ÷ CPI
VACRED
-120.6K h
Planned − Forecast
VAC = BAC − EAC
ETCN/A
636.2K h
Remaining hours
ETC = EAC − Spent Hours
Earned Value S-Curve
Discipline
DATA CENTER SAMPLE
Data Center Sample - Manpower
Work Schedule: Mon-Fri x 8 hrs/day
Discipline
Data Center Sample — Project Manpower (Monthly)
Schedule Health · Primavera P6
Critical Path
Controls_Star_Data_Center_120MW_30_Month_Current_Schedule_Gold_Standard_v2.xer
Refresh AI to AnalyzeCritical Paths
Top Controlling Paths — Start → Finish
Off Track · +105 Days
- Primary Critical Path — IFCOff Track · +105 DaysNotice to Proceed→Mass Grading→Data Hall 4 - Roof / Envelope→Data Hall 4 - L1 Documentation / QA Complete→Commercial Operation / Final Campus TurnoverDuration: 1,003 DaysPath Activities: 34Start: Jan 6, 2025Finish: Oct 6, 2027Currently working: Data Hall 4 - Roof / Envelope
- Secondary Critical PathNo clearly identifiable secondary critical path
- Tertiary Critical PathNo clearly identifiable tertiary critical path
Late Milestones
- Utility Witness / Backfeed2026-09-16
Slippage vs Approved Baseline
DAY 1 LOCKEDBaseline frozen 9/19/2026 · Controls_Star_Data_Center_120MW_30_Month_Baseline_Approved_Gold_Standard_v2.xer · 512 activities
Slipped
0
Recovered
0
Added
0
Removed
0
This schedule is still exactly on the approved baseline — no slippage since Day 1.
Discipline CPI & SPI
DATA CENTER SAMPLE
- CPI
- SPI
← swipe to see all disciplines →
Discipline Planned vs Earned vs Spent
DATA CENTER SAMPLE
- Earned
- Planned
- Spent
← swipe to see all disciplines →
AI Direction · GPT-5.6 Terra
CONTROLS STAR DIRECTION
Project Intelligence has not been generated yet.
Press Refresh Project Intelligence to have Controls Star read this project’s KPIs, S-curve trend, schedule network and critical paths — and tell you where to focus and why.
Discipline Detail Breakdown
Hours to date · through 2026-08-22
| Discipline | % Complete | Total Hours | Planned Hours | Earned Hours | Spent Hours | CPI | SPI | CPI/SPI Trend | Status |
|---|---|---|---|---|---|---|---|---|---|
| Civil | 100.0% | 180.0K | 180.0K | 180.0K | 187.5K | 0.96 | 1.00 | At Risk | |
| Engineering | 100.0% | 170.0K | 170.0K | 170.0K | 170.0K | 1.00 | 1.00 | On Track | |
| Concrete | 100.0% | 160.0K | 160.0K | 160.0K | 170.2K | 0.94 | 1.00 | At Risk | |
| Electrical | 56.3% | 470.0K | 314.5K | 264.4K | 293.8K | 0.90 | 0.84 | Off Track | |
| Mechanical | 61.3% | 300.0K | 220.9K | 184.0K | 200.0K | 0.92 | 0.83 | Off Track | |
| Procurement | 100.0% | 90.0K | 90.0K | 90.0K | 91.8K | 0.98 | 1.00 | At Risk | |
| Structural | 100.0% | 150.0K | 150.0K | 150.0K | 157.9K | 0.95 | 1.00 | At Risk | |
| Architectural | 76.9% | 100.0K | 94.4K | 76.9K | 78.5K | 0.98 | 0.81 | Off Track | |
| Substation/Interconnect | 66.4% | 90.0K | 79.0K | 59.7K | 65.6K | 0.91 | 0.76 | Off Track | |
| Controls | 49.9% | 130.0K | 82.9K | 64.9K | 69.1K | 0.94 | 0.78 | Off Track | |
| Commissioning | 0.0% | 120.0K | 0 | 0 | 0 | — | — | N/A | |
| Turnover | 0.0% | 40.0K | 0 | 0 | 0 | — | — | N/A |
Sample source files
Download the three files behind this project
These are the exact demonstration files that were imported to build this Sample Project. Open them, compare them with the page, or use them as a template for your own upload.
EVM Data
Excel workbook · Planned / Earned / Spent hours by discipline
Controls_Star_Data_Center_120MW_30_Month_EVM_Gold_Standard_v2.xlsx
Download sample file
Current Schedule
Primavera P6 XER · sets the project Data Date
Controls_Star_Data_Center_120MW_30_Month_Current_Schedule_Gold_Standard_v2.xer
Download sample file
Approved Baseline
Primavera P6 XER · On Track / Off Track comparison
Controls_Star_Data_Center_120MW_30_Month_Baseline_Approved_Gold_Standard_v2.xer
Download sample file
Demonstration project. Company, project, personnel, and performance data are fictional/sample data provided solely to demonstrate Controls Star.